Tenant Delays Clause Examples
The Tenant Delays clause defines the consequences and procedures when a tenant causes delays in a project or contractual timeline. Typically, this clause outlines what constitutes a delay attributable to the tenant, such as failing to provide necessary approvals, information, or access to the premises, and may specify remedies like extensions of time for the landlord or contractor, or additional costs payable by the tenant. Its core function is to allocate responsibility for project setbacks, ensuring that the landlord or service provider is not penalized for delays outside their control and that the tenant is incentivized to fulfill their obligations promptly.
POPULAR SAMPLE Copied 8 times
Tenant Delays.ĚýA "Tenant Delayâ€� shall be defined as any delay in the design, permitting or performance of the Base Building Work to the extent that such delay is actually caused by any act or, where there is a duty to act under this Lease, any failure to act by Tenant or Tenant's contractors, architects, engineers, or anyone else engaged by or on behalf of Tenant in connection with the construction of the Tenant Improvement Work as set forth in this Article III (including, without limitation, any delays resulting from the Approved Tenant Finishes under Section 3.l(C) above) and disclosed to Tenant as hereinafter provided. Notwithstanding the foregoing, in no event shall any delays in the completion of the Base Building Work caused by Tenant’s use of non-union labor constitute a Tenant Delay hereunder. Notwithstanding the foregoing, no event shall be deemed a Tenant Delay unless and until Landlord has given Tenant written notice (the "Tenant Delay Notice") advising Tenant: (x) that a Tenant Delay is occurring and setting forth Landlord's good faith estimate as to the likely length of such Tenant Delay; (y) of the basis on which Landlord has determined that a Tenant Delay is occurring; and (z) the actions which Landlord believes that Tenant must take to eliminate such Tenant Delay. No event shall be deemed to be a Tenant Delay unless and until Tenant has failed to rectify the situation causing the Tenant Delay within forty-eight (48) hours after Tenant's receipt of the Tenant Delay Notice (which for the purposes of determining receipt may be delivered by hand to Tenant's Construction Representative, with copies to follow to Tenant at the notice address set forth in Section 1.2 of this Lease within five (5) days thereafter); provided, however, that if Tenant shall fail to eliminate the delay within the aforesaid 48-hour period, then the 48-hour cure period shall be included in the period of time charged to Tenant pursuant to such Tenant Delay Notice (it being understood and agreed that if Tenant shall in fact eliminate the Tenant Delay within the 48-hour cure period, no Tenant Delay shall be deemed to have occurred for the purposes of this Article III). In addition, any delay to the extent caused by (i) Landlord Delay or (ii) subject to the limitations of subsection (D) below, Tenant's Force Majeure (as defined in said subsection (D)) shall not constitute Tenant Delay. Tenant covenants that no Tenant Delay shall delay commencement of the Term or the obligation to pay Annual...
Tenant Delays.ĚýThere shall be no extension of the scheduled commencement or expiration date of the term of the Lease (as otherwise permissibly extended under Paragraph 5 above) if the Work has not been substantially completed on said scheduled commencement date by reason of any delay attributable to Tenant ("Tenant Delays"), including without limitation:
(i) the failure of Tenant to furnish all or any plans, drawings, specifications, finish details or the other information required under Paragraph 1 above on or before the date stated in Paragraph 1;
(ii) the failure of Tenant to grant approval of the Working Drawings within the time required under Paragraph 2 above;
(iii) the failure of Tenant to comply with the requirements of Paragraph 4 above;
(iv) Tenant's requirements for special work or materials, finishes, or installations other than the Building Standards or Tenant's requirements for special construction staging or phasing;
(v) the performance of any Additional Work (as defined in Paragraph 7 below) requested by Tenant or the performance of any work in the Premises by any person, firm or corporation employed by or on behalf of Tenant, or any failure to complete or delay in completion of such work; or
(vi) any other act or omission of Tenant that causes a delay.
Tenant Delays.ĚýThe Commencement Date shall not be delayed or postponed due to Tenant Delays, and the Term, Tenant's obligations to pay Rent and all of Tenant's other obligations under this Lease shall commence upon the date which would have been the Commencement Date but for Tenant Delays.
Tenant Delays.ĚýThere shall be no extension of the scheduled Commencement Date or Expiration Date of the term of the Lease (as otherwise permissibly extended in accordance with the provisions of Section 6 above) if the Work has not been Substantially Completed by the scheduled Commencement Date due to any actual delay attributable to Tenant and/or Tenant’s Representatives or Tenant’s intended use of the Premises (collectively, “Tenant Delaysâ€�), including, but not limited to, any of the following described events or occurrences: (a) delays related to changes made or requested by Tenant to the Work and/or the Final Drawings after final approval by Landlord and Tenant of the Final Drawings; (b) the failure of Tenant to furnish all or any plans, drawings, specifications, finish details or other information required under Sections 3 and 4 above within the required time limits or, if no time limit is specified, in a prompt manner; (c) the failure of Tenant to comply with the requirements of Section 9 below; (d) Tenant’s requirements for special work or materials, finishes, or installations other than the Building Standards or Tenant’s requirements for special construction or phasing; (e) any changes required by the fire department, building or planning department, building inspectors or any other agency having jurisdiction over the Building, the Work and/or the Tenant Improvements if such changes are directly attributable to Tenant’s use or Tenant’s specialized tenant improvements; (f) the performance of any additional work pursuant to a Change Request (defined below in Section 9) which is requested by Tenant; (g) the performance of work in or about the Premises by any person, firm or corporation employed by or on behalf of Tenant, including, without limitation, any failure to complete or any delay in the completion of such work required to be performed in order for Substantial Completion to occur; or (h) any and all delays caused by or arising from acts or omissions of Tenant and/or Tenant’s Representatives, in any manner whatsoever, including, but not limited to, any and all revisions to the Final Drawings. Any actual delays in the construction of the Tenant Improvements due to any Tenant Delays, shall in no way extend or affect the date on which Tenant is required to commence paying Rent under the terms of the Lease. It is the intention of the parties that all of such delays will be considered Tenant Delays for which Tenant shall be wholly and completely responsible for any ...
Tenant Delays.ĚýFor purposes of this Work Letter, “Tenant Delaysâ€� means any delay in the completion of the Landlord’s Work resulting from any or all of the following:
Tenant Delays.ĚýAs used in this Lease, the term "TENANT DELAY" shall mean the period of an actual delay or delays in the Substantial Completion of Landlord's Work or in the occurrence of any of the other conditions precedent to the Delivery Date, as set forth in Article 8 of the Lease, to the extent resulting from:
Tenant Delays.ĚýIf the occurrence of any of the Occupancy Conditions and Landlord’s preparation of the Premises for occupancy shall be delayed owing to either (a) any act, omission, or failure of Tenant or any of its employees, agents, or contractors which shall continue after Landlord shall have given Tenant reasonable notice that such act, omission, or failure would result in delay, and such delay shall have been unavoidable by Landlord in the exercise of reasonable diligence and prudence; or (b) the nature of any items of additional work or change orders that Landlord undertakes to perform for the account of Tenant (including any delays incurred by Landlord, after making reasonable efforts, in procuring any materials, equipment, or fixtures of a kind or nature not used by Landlord as part of its standard construction) (collectively “Tenant Delaysâ€�), then the Premises shall be deemed ready for occupancy on the date when they would have been ready but for such Tenant Delays.
Tenant Delays.ĚýFor purposes of this Work Letter Agreement, "Tenant Delays" means any delay in the completion of the Tenant Improvements resulting from any or all of the following: (a) Tenant's failure to timely perform any of its obligations pursuant to this Work Letter Agreement, including any failure to complete, on or before the due date therefor, any action item which is Tenant's responsibility pursuant to the Work Schedule delivered by Landlord to Tenant pursuant to this Work Letter Agreement; (b) Tenant's changes to Space Plans or Final Plans after Landlord's approval thereof; (c) Tenant's request for materials, finishes, or installations which are not readily available or which are incompatible with the Standards; (d) any delay of Tenant in making payment to Landlord for Tenant's share of the Work Cost; or (e) any other act or failure to act by Tenant, Tenant's employees, agents, architects, independent contractors, consultants and/or any other person performing or required to perform services on behalf of Tenant.
Tenant Delays.ĚýIf there shall be a delay or there are delays in the Substantial Completion of the Premises (as a direct, indirect, partial, or total result of any of the following (collectively, “Tenant Delaysâ€�):
5.2.1 Tenant’s failure to timely approve any matter requiring Tenant’s approval, including a Partial Cost Proposal or the Cost Proposal and/or Tenant’s failure to timely perform any other obligation or act required of Tenant hereunder;
5.2.2 a breach by Tenant of the terms of this Tenant Work Letter or the Lease;
5.2.3 Tenant’s request for changes in the Construction Drawings;
Tenant Delays.ĚýFor purposes of this Agreement and the Lease, the following events shall constitute delays caused by Tenant (a "Tenant Delay"):
(a) Tenant's request for Change Orders whether or not any such Change Orders are actually performed; or
(b) Contractor's performance of any Change Orders; or
(c) Tenant's request for materials, finishes or installations requiring unusually long lead times; or
(d) Tenant's delay in reviewing, revising or approving plans and specifications beyond the periods set forth in the Performance Schedule; or
(e) Tenant's delay in providing information critical to the normal progression of the project. Tenant shall provide such information as soon as reasonably possible, but in no event longer than the time period specified herein, or if no time period is specified, one week after receipt of such request for information from the Landlord; or
(f) Tenant's delay in making payments to Landlord for costs of the Tenant Improvements and/or Change Orders in excess of the Tenant Improvement Allowance; or
(g) Any other act or omission by Tenant, its agents, contractors or persons employed by any of such persons, including Tenant's delay in execution this Lease. If any of the foregoing Tenant Delays occur, then Landlord shall cause Landlord's Architect to certify the date on which the Tenant Improvements would have been Substantially Completed but for such Tenant Delay, then such date shall constitute the Commencement Date for all purposes hereunder and Landlord and Tenant shall execute the Commencement Date Confirmation, confirming such date.